Checkpoint 1 - 2 | Checkpoint 3 | Checkpoint 4 | Road Works | Finishing Touches

Progress on the building is going smoothly with pace. Cement were poured onto the first floor platform 2 days ago. Thanks to the bright sunshine, the cement solidifies and dry up quicker than expected. Works on the 2nd floor can now begin. I can start packing my stuffs and get ready to move back to Miri soon :D

Checkpoint No.3

October 13th, 2007.
Temporary gate to the Lutong-Kuala Baram Highway
A temporary gate to the Lutong-Kuala Baram Highway. Provides an easy access for the lorries to unload sands and building materials.

Woods scattered
Scattered woods. Over tonnes of them are used so far.

Additional columns
This column wasn’t in the plan. The contractor suggested an additional columns be built to avoid cracks under heavy loads.

View of the Lutong-Kuala Baram Highway
Beautiful morning sky. Fantastic view on the first floor towards the Lutong-Kuala Baram highway.

Working on the mold for the 2nd floor columns
Labourers working on the mold for the 2nd floor columns.

The mold
The finished mold.

Rear end of the building
The rear end of the building. This will be turned into tarred pathway for cars to access the building.

Grassy land
There are 2 more lots of empty lands beyond the rear of the building.

The building is scheduled to be completed and handed over by January 2008. Watch out for the new age automotive store in Miri :D